Over the next year, the Webster School will undergo structural improvements, interior aesthetic and systems upgrades, and the addition of a new gymnasium; providing the community with a 21st century learning environment. Scroll below for the latest update on construction activities. For a historic narrative on Webster school reference the Seattle Public Schools book: Building for Learning: Seattle Public School Histories, 1862-2000 by Nile Thompson and Carolyn J. Marr.
Project Milestone Dates Demolition Start:6/18/2019 Existing Building Structural Upgrades Start:7/23/2019 Existing Building Structural Steel Upgrades Start: 11/1/2019 Gym Addition Start: 12/10/2019 Right-of-way Street Improvements Start: 1/22/2020 Interior Finishes Start: 2/12/2020 Gym Addition Complete: 5/6/2020 Interior Finishes Complete: 6/5/2020 City of Seattle Final Building Inspection: 7/20/2020 First Day of School: 09/02/2020
June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020 July 2020