Mountlake Terrace Elementary School Replacement Project
Project Milestone Dates
School Out: 06/28/17
Demolition Start: 07/10/17
Structure Complete: 01/15/18
Roof Complete: 06/22/18
Exterior Complete: 06/29/18
Interior Complete: 07/27/18
Site Improvements Complete: 07/27/18
Substantial Completion: 07/27/18
Opening Date
09/05/18
School Out: 06/28/17
Demolition Start: 07/10/17
Structure Complete: 01/15/18
Roof Complete: 06/22/18
Exterior Complete: 06/29/18
Interior Complete: 07/27/18
Site Improvements Complete: 07/27/18
Substantial Completion: 07/27/18
Opening Date
09/05/18