Lynnwood Elementary School Replacement Project

Picture
Project Milestone Dates
School Out: 06/28/17
Demolition Start: 07/10/17

Structure Complete: 11/30/17
Roof Complete: 05/31/18
Exterior Complete: 06/29/18
Interior Complete: 07/27/18
Site Improvements Complete: 07/27/18
Substantial Completion: 07/27/18

Opening Date
09/05/18

Construction
​Web Camera


Interested in what is happening during the Lynnwood Elementary School Replacement project? Take a look at our live web cam by clicking on the image to ​the right!
Picture

Progress Photos

Below are progress photos from July 2018 of the Lynnwood project site.

Videos

June 2018 Time-Lapse
May 2018 Time-Lapse
April 2018 Time-Lapse
March 2018 Time-Lapse
February 2018 Time-Lapse
January 2018 Time-Lapse
December 2017 Time-Lapse
November 2017 Time-Lapse
October 2017 Time-Lapse
September 2017 Time-Lapse
August 2017 Time-Lapse
July 2017 Time-Lapse

Media

Edmonds School District Lynnwood Elementary Information

Click Here For More Information!

Social Media

Picture

Picture
Picture

Monthly Reports

Proudly powered by Weebly